Work Orders Rescheduling Within The Planning Time Fence
(Doc ID 795155.1)
Last updated on MAY 15, 2023
Applies to:
Oracle Advanced Supply Chain Planning - Version 12.0 and laterInformation in this document applies to any platform.
Symptoms
Work Orders that have a start date prior to the anchor date are being rescheduled within the Planning Time Fence. The issue appears to occur when the planned anchor dates are greater than the batch start date. Find that Work Orders with a start date prior to the anchor date are being rescheduled within the Planning Time Fence
STEPS:
Run MRP with a work order that starts in the past.
Profile Option MSC : Firm Work Orders/Operation within Time Fence set to Yes
There is a consequent Planning Time Fence for this item (2 months)
ASCP suggests a rescheduling of the batch, 'Reschedule in' and violates the Planning Time Fence
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |