Calculations For Apply Actuals Option: "When Actuals Are Applied From Timesheets, Calculate Activity Remaining Durations" (Doc ID 892691.1)

Last updated on MARCH 22, 2023

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
Primavera P6 Professional Project Management - Version 5.0 and later
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 8.2.4.0 and later
Primavera P6 Standard Project and Portfolio Management Cloud Service - Version 16.2.13.0 and later
All Platforms

Goal

This document explains the calculations for Apply Actuals option: "When actuals are applied from timesheets, calculate activity remaining durations"

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
 "Always recalculate" Option
 "Based on activity duration type" Option
 Fixed Duration and Units/Time
 Fixed Duration and Units
 Fixed Units
 Fixed Units/Time