How To Set Planned Dates Equal To Start And Finish Dates Using Global Change (Doc ID 900195.1)

Last updated on MAY 23, 2017

Applies to:

Primavera P6 Enterprise Project Portfolio Management - Version 5.0 and later
Primavera P6 Professional Project Management - Version 5.0 and later
All Platforms
***Checked for relevance on22-JAN-2013***
***Checked for relevance on 27-Apr-2015***

Goal

This document explains how to run a Global Change to set Planned Start and Planned Finish Dates equal to the Start and Finish Dates.

Solution