Goal

We have a performance document FY15 Project Evaluation Manager that has a task Manage Participant Feedback with due date 16/05/2015
The problem is that the participants are still able to submit the evaluations today 18/05/2015.

After the due date the Manager can't send the requests to the participants. How it is possible to block also for the participants?
 