Baselines Are Published When No Changes Are Made to the Baseline (Doc ID 2325896.1)

Last updated on OCTOBER 19, 2023

Applies to:

Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 16.2.6.0 and later
Primavera P6 Enterprise Project Portfolio Management - Version 16.2.6.0 and later
Information in this document applies to any platform.

Symptoms


ACTUAL BEHAVIOR

When publishing a project, all baselines that had publication enabled will also publish, even though no changes were made to the baselines.

EXPECTED BEHAVIOR

Should just publish the projects that had changes made to baselines.

STEPS

The issue can be reproduced at will with the following steps:

  1. Login to P6
  2. Ensure Publish Baselines is enabled
  3. Ensure Project has publication enabled, and all baselines have publication enabled.
  4. Publish project and baselines
  5. On first run, all baselines will be published
  6. After publication completes, make some changes to parent project (assign activity codes, etc)
  7. Publish Parent Project (Actions>Run>Publish)
  8. Project and all baselines are published even though no changes were made to Project.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.