My Oracle Support Banner

How to Withdraw the Workflow for Submitted Award Project Budget Approval? (Doc ID 2393673.1)

Last updated on MAY 31, 2023

Applies to:

Oracle Fusion Grants Management Cloud Service - Version 11.13.17.11.0 and later
Information in this document applies to any platform.

Symptoms

On : 11.13.17.11.0 version, Manage Awards

ACTUAL BEHAVIOR
---------------
Users can't baseline project budget. This is due to having an active contract/award/project with matching dates, and active PM.
Therefore no expenditures can be processed against this grant.
This is also holding up invoices from being accounted.

EXPECTED BEHAVIOR
-----------------------
Budget has been submitted for approval but it did not approved and base lined

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create the award
2. Create the project and associated to award
3. Create the project budget and submitted for baseline
4. Its not baselined, still showing in submitted status

BUSINESS IMPACT
-----------------------
The issue has the following business impact:
Due to this issue, users cannot baselined the budget

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.