Master KM: Guide to Manufacturing Calendar and Resource Scheduling (Setup, FAQ, Troubleshooting)
(Doc ID 2657499.1)
Last updated on FEBRUARY 21, 2023
Applies to:
Oracle Fusion Manufacturing Cloud ServiceInformation in this document applies to any platform.
Purpose
The purpose of this document is to provide a complete guide to implementers on calendar setups and resource scheduling on manufacturing cloud.
Scope
This document will guide implementation teams through calendar setups and resource scheduling in manufacturing, address frequently asked questions and help troubleshoot common issues.
Details
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Purpose |
Scope |
Details |
What is a manufacturing calendar/schedule? |
Schedule/Calendar Setups |
Set up work shifts |
Time Shifts |
Duration Shift |
Elapsed Shift |
Set up work day pattern |
Set up schedule exceptions |
Set up schedules/calendars |
Setting up Manufacturing Schedule using Calendar/Schedule |
Frequently Asked Questions (FAQ) |
What timezone determines the start date / end date of a work order for scheduling? |
Does manufacturing cloud support overlapping shifts? |
What is the impact of modifying calendar/schedule on plant parameters to add additional shifts or modifying resources to 24 hours after creating transactions in the plant? |
Will a facility schedule change impact work orders already created? |
Is it possible to have Resource UOMs other than time based which can be used for Costing and Scheduling? |
Is it possible to schedule the work order at the resource instance level? |
Is there any relation between the resource calendar and the project resource management? |
When user created a work order on Friday, the start date moves to next day. Why has start date moved to next day? |
Why is planning suggested due date not enforced as the "Completion Date" for the work order? |
Can work order end date/start date be scheduled beyond year( 53 weeks)? |
What is the equivalent terms in fusion manufacturing cloud for e-business suite (EBS) "Lot" and "Item" Basis? |
How to define a manufacturing schedule shift with a break? |
Is it feasible to share a resource in one work center with another work center? |
Troubleshooting |
Tips for troubleshooting resource scheduling |
Common Issues |
Work definition error - "The exception start time cannot be earlier than the associated shift time and the end time cannot be later than the associated shift time. (RCS-3360123)" |
The work order start and end date are the same |
You cannot enable the schedule indicator because the class of UOM set in the Hour UOM profile option does not match the Service Duration Class profile option |
No calendar is available for assignment in the Manage Plant Parameters setup task though calendar is defined. |