Scheduling Is Slow After Making A Relationship Change In EPPM
(Doc ID 2677901.1)
Last updated on OCTOBER 19, 2023
Applies to:
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 19.12.3.0 to 19.12.5.0 [Release 19.12]Information in this document applies to any platform.
Symptoms
Once logged into P6 Web, after making a relationship change and then scheduling the project, the scheduling takes a long time to complete.
Steps to Reproduce
- Log into P6 Web
- Projects - EPS tab.
- Open Project.
- Activities tab.
- Select an activity
- In the bottom Details, select Relationships tab.
- Assign or remove a relationship.
- Click Schedule - Schedule now.
- Scheduling takes "minutes to complete".
Note: If NO relationship change is made, the same scheduling takes seconds.
If the relationships tab is removed AND a refresh operation is performed prior to scheduling, the scheduling time will be reduced.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |