Capital Asset Is Showing Different Value In Projects Vs Assets
(Doc ID 2745329.1)
Last updated on SEPTEMBER 02, 2023
Applies to:
Oracle Fusion Project Costing Cloud Service - Version 11.13.20.10.0 and laterInformation in this document applies to any platform.
Symptoms
On : 11.13.20.10.0 version, Capitalize Assets And Interest
ACTUAL BEHAVIOR
Capital Asset is showing incorrect data data
We see that the total asset cost showing on 'Manage Capital Assets' screen of below asset is not matching with the sum of amounts on the asset lines page for the asset.
Project Number: PNUMBER
Project Name: PNAME
Asset Name: ASSETNAME
Amount on Manage Capital Assets screen: VALUE1
Sum of asset lines for the Asset: VALUE2
EXPECTED BEHAVIOR
The costs on Manage capital assets should match the total of the assets lines for the asset Asset Name: ASSETNAME on the Project Project Name: PROJECTNAME , Project Number: PNUMBER
STEPS
The issue can be reproduced at will with the following steps:
1. Verify the costs on Manage capital assets : Total Asset Cost: VALUE1
2. Verify the assets lines: Raw Cost total: VALUE2
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |