32612499. After Task Is Moved In MSP, Task Number Is Not Synchronized With Oracle
(Doc ID 2769383.1)
Last updated on SEPTEMBER 02, 2023
Applies to:
Oracle Fusion Project Foundation Cloud Service - Version 11.13.20.10.0 and laterInformation in this document applies to any platform.
Goal
While testing different use cases for the integration between Oracle Project Financial Management Cloud and Microsoft Projects (MS), we moved a task in the MS Project plan and this action changed the attribute "Outline Number" which is supposed to be sycnhronized with Oracle's Task Number.
But after synchronizing the update PS Plan to Oracle, the task number did not change. Why is this?
Solution
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Goal |
Solution |
References |