Correct Baseline Budget Amount Does Not Showed Up
(Doc ID 2774562.1)
Last updated on AUGUST 31, 2023
Applies to:
Oracle Fusion Project Control Cloud Service - Version 11.13.20.10.0 and laterInformation in this document applies to any platform.
Symptoms
On : 11.13.20.10.0 version, Project Budget
ACTUAL BEHAVIOR
Correct baseline budget amount does not showed up when baselining.
EXPECTED BEHAVIOR
Correct baseline budget amount to show up when baselining.
STEPS
The issue can be reproduced at will with the following steps:
1. Create budget version manually or by import
2. Baseline - the correct amount is not showing up
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |