CIP Asset Addion: System Does Not Allow CIP Addition with Cost. Cost Field is Grey Out.
(Doc ID 2788560.1)
Last updated on JULY 18, 2021
Applies to:
Oracle Fusion Assets Cloud Service - Version 11.13.21.01.0 and laterOracle Fusion Assets - Version 11.12.1.0.0 and later
Information in this document applies to any platform.
Symptoms
When adding CIP assets manually in the UI, through the Add Asset task, the Cost field appears greyed out in the Add Asset pop-up.
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Go to Assets -> Tasks panel -> Add Asset task
2. Select Asset Type = CIP
3. Noticed that the Cost field become greyed out with amount = 0.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |