Symptoms


Scenario explained below has one Network with 2 legs, one leg with the Ground Schedule and another leg to allow planning without Ground Schedule

01. 21 Orders (with varying weight, volume ship unit) are bulk planned
02. 19 Orders get planned on to a ground schedule shipment & exhausts the capacity of the associated equipment group(So far so good)
03. Remaining 2 order movements fail

Expectation is that these 2 orders should get planned on to regular shipment




Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution