OTM Planning Not Considering Ground Schedule Capacity When Routing Order To Different Legs
(Doc ID 2789477.1)
Last updated on DECEMBER 07, 2023
Applies to:
Oracle Transportation Operational Planning Cloud Service - Version 21.1 to 21.1 [Release 21]Information in this document applies to any platform.
Symptoms
Scenario explained below has one Network with 2 legs, one leg with the Ground Schedule and another leg to allow planning without Ground Schedule
01. 21 Orders (with varying weight, volume ship unit) are bulk planned
02. 19 Orders get planned on to a ground schedule shipment & exhausts the capacity of the associated equipment group(So far so good)
03. Remaining 2 order movements fail
Expectation is that these 2 orders should get planned on to regular shipment
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |