Symptoms

When Global Procurement Supply Chain Financial Orchestration is setup, the Accrue at Receipt flag defaults to checked on Purchase Order (PO) schedules for 2-way match lines. These POs are created through integration from upstream system and status for 2-way match lines changes to "Closed for Receiving" as soon as they are created as no receipt is required.

Also this is observed only when SCFO flow is being derived on a PO. When a Standard PO is created, where SCFO is not called, Accrue at Receipt is unchecked for 2-way match lines.

The issue is that the Accrue at Receipt flag is yes for Global Procurement Purchase Orders for Expense Type for SCFO PO's and this flag needs to be avoided.
More details:

1. 2 way match po schedule lines (service)
2. creating this purchase order with closed for receiving.
3. in global procurement flow, always purchase order lines are getting defaulted to accure at receipt flag to 'Y'.
4. Per Global procurement flow design, accrue at receipt flag is yes.
5. SSP receiving allows to create receipt for service based purchase orders.
6. Business process requires not to create SSP Receiving for these purchase orders (Global Procurement process requires this step).

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.