Why Is Permitted To Entered Task Start Date Earlier Than The Project Start Date?
(Doc ID 2814655.1)
Last updated on OCTOBER 12, 2023
Applies to:
Oracle Fusion Project Management Cloud Service - Version 11.13.21.07.0 and laterInformation in this document applies to any platform.
Goal
On : 11.13.21.07.0 version, Define Project Plan & Schedule
Entered start date is earlier than project start
The user opens a project in Project Management and tries to change a date but found an issue.
Infact start date of task can be antecedent to project start date and this is not correct .
Solution