Project Performance Reports - In This Month End, All Projects Have EAC Amount Doubled (Doc ID 2829519.1)

Last updated on AUGUST 08, 2024

Applies to:

Oracle Fusion Project Control Cloud Service - Version 11.13.21.10.0 and later
Information in this document applies to any platform.

Symptoms

On : 11.13.21.10.0 version, Project Forecast

ACTUAL BEHAVIOR

After 21D Forecast Current Working & Current Approved version both have Primary cost forecast flag Y . When capturing project performance. In this month end, all projects shoud not have EAC amount doubled.


EXPECTED BEHAVIOR

When capturing project performance. In this month end, all projects shoud not have EAC amount doubled.

STEPS

The issue can be reproduced at will with the following steps:
1. After 21D Upgrade, a few reports on capturing project performance, in this month end, all projects have EAC amount doubled.
2. After engaging report team , the user has been advised that the double up of EAC balance is from 2 forecast versions are having Primary cost forecast flag.
3. After checkeing from front end, projects only have one Current Approved version, and one Current Working version.
However both of them are having the flag 'Primary cost forecast flag' set to 'Y' therefore were included in the report.
This issue didn't happen before, and the user believes the 'Current working' version should not have this flag set to Y.

 
Due to this issue, users cannot conciliate the forecast amount

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.