Symptoms

When attempting to cancel a second PO schedule via a change Order
the following error occurs.

ERROR
-----------------------
You must undo your changes before canceling this line or schedule. (PO-2055089)


STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Create a purchase requisitions via REST API, approve
2. Buyer creates PO via Process Requisition UI, approves PO, this PO is interfaced to primavera
3. Primavera triggers a partial payment to supplier for line 1, then via REST API splits the schedule in two, 1 for the payment and 2 schedule with the remaining qty/amount of the PO Line
4. Buyer creates a change order, cancel schedule # 2 and is ok, then selects any other schedule to be cancelled in same CO and gets the error


Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.