Budget Synchronization While Baseline Budget, It Does Not Immediately Reflect
(Doc ID 2850670.1)
Last updated on SEPTEMBER 02, 2023
Applies to:
Oracle Fusion Project Costing Cloud Service - Version 11.13.21.10.0 and laterInformation in this document applies to any platform.
Goal
On : 11.13.21.10.0 version, Budgetary Control/Encumbrance Accounting
Budget Synchronization
We have an issue where once we have a baseline budget, it does not immediately reflect. During period close due to budget deficiencies we have issues where transactions are failing during Requisition creation, Receipt accounting transactions etc. We update the budget however it takes until the next day when the transactions are able to process.
Is there any job that needs to be run once the budget has been updated/baselined?
Solution