Importing P6 Project (XER or XML) With Calendar Exception Ending Time at 12:00AM Can Cause Invalid Time in Standard Calendar
(Doc ID 2918506.1)
Last updated on JANUARY 03, 2023
Applies to:
Oracle Primavera Cloud Service - Version 22.10 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
Importing a P6 Project (XER or XML type) containing Calendar exceptions with ending time at 12:00AM will result in invalid time entries to Standard calendar, which can cause incorrect, negative float calculations.
EXPECTED BEHAVIOR
During import handle Calendar exceptions ending times at 12:00AM.
STEPS
The issue can be reproduced at will with the following steps:
- Export P6 project with Exception (non-Standard) ending time at 12:00AM
- Import P6 project (XER or XML) into OPC
- Result: Certain P6 calendar Exception ending times (12:00AM) are assigned to Standard workday, which can cause negative float
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |