Resource Usage Histogram Displays Planned Curve One Day Before Start Date (Doc ID 2940441.1)

Last updated on APRIL 06, 2023

Applies to:

Oracle Primavera Cloud Service - Version 23.3 and later
Information in this document applies to any platform.

Symptoms

ACTUAL BEHAVIOR

When viewing the Resource Usage Histogram, the current schedule curve displays the correct date, however the planned/baseline curve is drawn 1 day prior.

EXPECTED BEHAVIOR

The current and planned curves should match.

The issue can be reproduced at will using the following steps:

  1. View a project with a baseline.
  2. Select Schedule > Activities > Project Usage (lower tab).
  3. Select Resource Usage > Not Stacked Histogram.
  4. Result: Planned curve starts 1 day prior to start date.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.