Resource Usage Histogram Displays Planned Curve One Day Before Start Date
(Doc ID 2940441.1)
Last updated on APRIL 06, 2023
Applies to:
Oracle Primavera Cloud Service - Version 23.3 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
When viewing the Resource Usage Histogram, the current schedule curve displays the correct date, however the planned/baseline curve is drawn 1 day prior.
EXPECTED BEHAVIOR
The current and planned curves should match.
The issue can be reproduced at will using the following steps:
- View a project with a baseline.
- Select Schedule > Activities > Project Usage (lower tab).
- Select Resource Usage > Not Stacked Histogram.
- Result: Planned curve starts 1 day prior to start date.