Why Showing Two Lines In Fixed Assets Source Line Information ?
(Doc ID 2953594.1)
Last updated on SEPTEMBER 03, 2023
Applies to:
Oracle Fusion Project Costing Cloud Service - Version 11.13.23.01.0 and laterInformation in this document applies to any platform.
Goal
On : 11.13.23.01.0 version, Capitalize Assets And Interest
Why Transfer Projects Assets to Fixed Assets ( Generate Assets Lines+Tieback processes) is transffering two lines in Fixed Assets for a single asset?
We are transferring the Asset lines from Projects Costing to Fixed Assets.
We have only one asset line when transferring but when we import into Fixed assets, we see two lines; one with zero cost and other with the actual cost.
Business would like to have only one line in FA. Is there any configuration that controls it? Attached our configurations and data.
Solution