Store Period Performance Does Not Progress Beyond 20% for Large Projects
(Doc ID 2991537.1)
Last updated on FEBRUARY 21, 2024
Applies to:
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 23.7 and laterInformation in this document applies to any platform.
Symptoms
Store Period Performance for large projects is hanging at 20%. The application does not recover and must be ended via Task Manager.
STEPS TO REPRODUCE:
- Open the Project.
- Select Tools - > Store Period Performance.
- Change financial period to the current week.
- Click Store Now.
- The process goes up to 20% and then hangs.
- The Project Management process must be ended via Task Manager.
Cause