Import from Microsoft Project (MSP) XML Causes Units to be Different
(Doc ID 2991596.1)
Last updated on DECEMBER 07, 2023
Applies to:
Oracle Primavera Cloud Service - Version 23.1 and laterInformation in this document applies to any platform.
Symptoms
ACTUAL BEHAVIOR
When Importing a Project from MSP XML to OPC, the Project Activity Resource Assignments Units seem to change.
EXPECTED BEHAVIOR
OPC and MSP Project to have the same values.
STEPS
The issue can be reproduced at will with the following steps:
- Login to OPC
- Navigate to View all Projects.
- Select Actions, Import/Export - Microsoft Project and select Import and the MSP file.
- Notice on the imported file that the Activity Resource Assignments are different from the original Project.
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |