Error: 'The Planned Nonlabor Cost Field is Read-only (PRM-000000046),' When Trying to Update the Field per Activity.
(Doc ID 3017401.1)
Last updated on APRIL 24, 2024
Applies to:
Oracle Primavera Cloud Service - Version 18.1 and laterInformation in this document applies to any platform.
Symptoms
When attempting to Import a Project, the Planned Non-Labor Costs are not getting updated per Activity. When trying to individually enter the costs for each Activity, receive the following error:
ERROR:
The Planned Nonlabor Cost field is read-only.
(PRM-000000046)
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Import P6 Schedule into OPC.
2. Verify 'Planned Nonlabor Costs' field is not updated.
Cause
To view full details, sign in with your My Oracle Support account. |
|