In Team Member When a Primary Resource Marks an Assignment as Complete the Actual Finish Date Applied to the Activity Is Way out in the Future
(Doc ID 3020546.1)
Last updated on JULY 30, 2024
Applies to:
Primavera P6 Enterprise Project Portfolio Management Cloud Service - Version 23.12 and laterPrimavera P6 Enterprise Project Portfolio Management - Version 23.12 and later
Information in this document applies to any platform.
Symptoms
In Team Member when a Primary Resource marks an assignment as Completed, and after the TM Status update is Accepted (approved) in P6 Web, the Actual Finish date applied to the Activity is way out in the future.
STEPS TO DUPLICATE:
1. Schedule an activity with a Primary Resource that has a Finish date in the future
2. In P6 Team Member the Primary Resource marks the Activity as Completed
3. In P6 Web > Approval tab TM Status update is Accepted
* NOTE: the Project DD is 2/20/2024 and system date is 2/22/2024
4. Result 1 - Assignment Actual Finish Date applied correctly (2/22/2024)
5. Result 2 - Activity ID Actual Finish Date applied, unexpectedly, in the future (3/6/2024).
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Cause |
Solution |
References |