P6 XER PROJECT IMPORT FAILED TO COMPLETE (NPE - PLANSTARTDATE IS NULL)
(Doc ID 3025919.1)
Last updated on JUNE 07, 2024
Applies to:
Oracle Primavera Cloud Service - Version 24.4 and laterInformation in this document applies to any platform.
Symptoms
P6 XER Project Import Failed to Complete
ERROR
-----------------------
Import failed to complete successfully due to an exception. NullPointerException: Cannot invoke 'java.util.Date.after(java.util.Date)
because the return value of 'com.oracle.pgbu.common.entity.Project.getPlanStartDate()'' is null
STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Import Xer file into OPC
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |