To detail a set of steps that can be used to apply a PSU using opatch auto to Primary and Standby sites that are part of a Data Guard Physical Standby implementation. The process detailed takes into account Oracle Restart configurations where the GRID Infrastructure is installed in the environment and needs to be patched along with the RDBMS installation.


Process Overview

Phase 1: Ensure ALL prerequisites set out in the patches/PSU's README for applying the patch are met

Phase 2: Disable log shipping between the sites

Phase 3: Apply the Patch/PSU to the Standby site

Phase 4: Apply the Patch/PSU to the Primary site

Phase 5: Post patch application processes and checks


Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms