Node 1 Migration and Recommission on Oracle Big Data Appliance V4.11 and Higher
(Doc ID 2530489.1)
Last updated on JULY 20, 2024
Applies to:
Big Data Appliance Integrated Software - Version 4.11.0 and later Linux x86-64
Purpose
This note provides the details to migrate Node 1 of the cluster and then recommission Node 1. These steps would be used if the roles on Node 1 are migrated to newer hardware. It is not possible for Node 1 recommission to follow Node 1 migration if Node 1 has failed. In that case Node 1 needs to be reimaged and reprovisioned back into the cluster.
Note that Node 1 refers to the node with the Node 1 role.
Scope
Someone performing Node 1 migration and recommission to migrate Node 1 roles to newer hardware for example.
Details
To view full details, sign in with your My Oracle Support account.