ASCP-OPM - No dependent Demand Created for Component regarding Planned Order of Product (Doc ID 1178823.1)

Last updated on NOVEMBER 03, 2016

Applies to:

Oracle Process Manufacturing Process Planning - Version 11.5.10 and later
Information in this document applies to any platform.
***Checked for relevance on 16-JUL-2013***

Symptoms


On :  11.5.10 version, ASCP with OPM
Find that there is ingredient (component) demand for a planned order in an ASCP
  In Advanced Supply Chain Plan, demand exists for product 1002024, but this is not resulting in demand for a component of this product, 3001244.

EXPECTED BEHAVIOR
-----------------------
Expect the to get a dependent demand for ingredient item 3001244

STEPS
-----------------------
The issue can be reproduced at will with the following steps:
1. Run the Standard Collection, complete refresh
2. Run the Unconstrained ASCP Plan
3. view the missing data in the Planner Workbench
Navigate to Workbench
Choose organization BFG:CMF
3.View supply/demand criteria: item. equals 1002024/3001244
View horizontal plans for these items.
4.Demand for 1002024 has not resulted in expected demand being generated for the component 3001244.
5.On examining components of 1002024 in planning workbench. none are shown.

BUSINESS IMPACT
-----------------------
The issue has the following business impact: users cannot plan for ingredients

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms