ORA-00054: Resource Busy And Acquire With Nowait Specified When Updating Financial Plans
(Doc ID 1276247.1)
Last updated on OCTOBER 04, 2024
Applies to:
Oracle Project Planning and Control - Version 12.1.3 and laterInformation in this document applies to any platform.
Goal
User is getting the following errors when trying to approve, baseline, etc. financial plans:
This plan version is being updated by another process. Please wait and resubmit your process.
ORA-00054: resource busy and acquire with NOWAIT specified or timeout expired in Package PJI_FM_XBS_ACCUM_MAINT Procedure WBS_HEADERS_LOCK
ORA-00054: resource busy and acquire with NOWAIT specified or timeout expired in Package PJI_FM_XBS_ACCUM_MAINT Procedure PLAN_BASELINE_PVT
ORA-00054: resource busy and acquire with NOWAIT specified or timeout expired in Package PJI_FM_XBS_ACCUM_MAINT Procedure PLAN_BASELINE
ORA-00054: resource busy and acquire with NOWAIT specified or timeout expired in Package PA_FIN_PLAN_PVT Procedure Baseline_FinPlan
User-Defined Exception in Package PA_FIN_PLAN_PUB Procedure Baseline
How can these errors be eliminated?
Solution
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Goal |
Solution |
References |