Is it Possible to Unfreeze a Final Cost Update Done in Error in OPM Release 11i? (Doc ID 1278418.1)

Last updated on JUNE 23, 2016

Applies to:

Oracle Process Manufacturing Inventory - Version 11.5.10 to 11.5.10.2 [Release 11.5]
Information in this document applies to any platform.

Goal

We need assistance in unfreezing a frozen OPM cost period.  A run of Cost Update with the 'Final' flag checked by mistake.

No final Subledger Update or transfer to GL has been done, but there are additional transactions which we need to enter which are going to affect Item Costs.

Is it possible to unfreeze the period?

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a