R12 Commitments Do Not Appear In Project Status Inquiry (PSI) After running PRC: Update Project Summary Amounts Process
(Doc ID 1321003.1)
Last updated on APRIL 08, 2024
Applies to:
Oracle Project Planning and Control - Version 12.1.1 and laterInformation in this document applies to any platform.
Symptoms
New commitments do not appear in the Project Status Inquiry (PSI) form after running the concurrent program "PRC: Update Project Summary Amounts."
However, these same commitments appear when the PRC: Refresh Project Summary Amounts program is run.
Additional symptoms include:
Project Status Inquiry - Purchase order isn't displayed after creating a new project
If users create a new project and after that a project-related purchase order, the PO is not displayed as a commitment. Even if users create a project-related requisition than the requisition and the first created purchase order will be displayed.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
References |