Symptoms

When baselining budgets, the following errors are received:

1. This plan version is locked by another user
2. ORA-54: resource busy and acquire with NOWAIT specified in Package PJI_FM_XBS_ACCUM_MAINT
Procedure WBS_HEADERS_LOCK
3. ORA-54: resource busy and acquire with NOWAIT specified in Package PJI_FM_XBS_ACCUM_MAINT
Procedure PLAN_BASELIME_PVT
4. ORA-54: resource busy and acquire with NOWAIT specified in Package PJI_FM_XBS_ACCUM_MAINT
Procedure PLAN_BASELINE
5. ORA-54: resource busy and acquire with NOWAIT specified in PackageFIN_PLAN_PVT Procedure Baseline_FinPlan
6. User-Defined Exception in Package PA_FINPLAN_PUB Procedure Baseline

But the plan version is not locked by any user.

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.