R11 R12 Closed Purchase Orders Showing As Commitments In Project Status Inquiry (PSI) While Project is not Enabled for Funds Check (Doc ID 1382330.1)

Last updated on NOVEMBER 15, 2022

Applies to:

Oracle Project Planning and Control - Version 11.5.10.2 to 12.1.3 [Release 11.5.10 to 12.1]
Information in this document applies to any platform.

Symptoms

Project Status Inquiry (PSI) form shows 'Closed' and 'Planned' purchase orders as commitments even when corresponding project on Purchase Order (PO) Distribution is not funds check enabled.

EXPECTED BEHAVIOR
-----------------------
PSI screen shows 'Closed' and 'Planned' purchase orders as commitments only when corresponding project on PO Distribution is funds check enabled . Users do not consider releases on Planned PO as commitment if funds check is enabled for the project.

 

Changes

Create PO for a project which is not funds check enabled.   Close the PO.
Run PRC:Update Project Summary Amounts. Verify the record in PSI, it is still shown as commitment.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.