How to Handle Business Case in Order to Correctly Spread Items/Resource Costs to all Products in Batches if Regularly Changing Cost Allocation Factor after Batch release? (Doc ID 1468052.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Process Manufacturing Financials - Version 12.1 to 12.1.3 [Release 12.1]
Information in this document applies to any platform.

Goal

On : 12.1

Your goal is to to Allocate resource cost to all products produced in the Batch
You have say 5 products coming out in 1 process But total items/resources cost is getting allocated on only one product in the batch..

You expected Actual cost to Allocate/spread resource cost to all products produced in the Batch depending on each product's cost allocation factor with having following context:
1. Have a batch with 5 products coming out in 1 process
2. The cost allocation factor is spread among the 5 products
2. Run Actuall Cost: Total resources cost is getting allocated on only one product in the batch.

Why is this result?
 

Solution

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms