R12: PRC: Generate Financial Plan Amounts Does Not Create Forecast (Doc ID 1537253.1)

Last updated on JUNE 14, 2017

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

When attempting to run the PRC: Generate Financial Plan Amounts process,forecast amounts are not created and shows the following error:

ERROR
-----------------------
PA PRC: Generate Financial Plan Amounts does not create forecas
roject Name :TK unit test1 Financial Plan Type :Forecast
The Financial Planning Procedures have been called incorrectly: &PROCEDURENAME , &STAGE
Cause: Parameters passed to some of the procedures are invalid/insufficient.
Action: Contact your System Administrator.
Amounts cannot be generated because no source financial plan is available.
Project Name :TK unit test1 Financial Plan Type :Forecast
The Financial Planning Procedures have been called incorrectly: &PROCEDURENAME , &STAGE
Cause: Parameters passed to some of the procedures are invalid/insufficient.
Action: Contact your System Administrator.
Amounts cannot be generated because no source financial plan is available.

 

The user will then enter the Plan Type parameter and re-run the process but the error no longer appears but amounts are still not generated on the
version. Amounts are generated fine when generating forecast amounts in self-service however it is not possible to do so via the concurrent process.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms