Engineer Bom Fail To Transfer Manufacturing With Error ENG_TRANSFER_PENDING_DG Or Same Error Observed In ENCACNC Module: Engineering Change Order Implementation (Doc ID 1900194.1)

Last updated on MARCH 15, 2024

Applies to:

Oracle Engineering - Version 12.1.3 and later
Information in this document applies to any platform.
ENCACNC module: Engineering Change Order Implementation

Symptoms

When attempting to Perform Transfer To Manufacturing in Engineering, the following error occurs.

ERROR
ENG_TRANSFER_PENDING_DG

* Translation of error code:
Cannot transfer item &ITEM_NAME, because it has one or more pending engineering delete groups.

STEPS
1. Naigate to Engineering>prototypes>Transfer to Manufacturing
2. Enter item details.
3. Try to transfer.
4. Receive error.

Also, similar results are observed if customer runs Engineering Change Order Implementation conc program, as observed in the log:

ENCACNC module: Engineering Change Order Implementation
Argument 1 (ORG_ID) = 142
Argument 2 (ALL_ORG_FLAG) = 2
Argument 3 (ORG_HIERARCHY) =
Argument 4 (CHANGE_NOTICE) = ECO-001422
Argument 5 (REVISED_ITEM_SEQUENCE_ID) =
Argument 6  =

l_return_status: 0  (0-Success, 1-Error)
After Calling to ENGPKIMP.Update_BSB_Request_Id_Column to get the lock on row
Failure in enimpri_implement_revised_item (eco_failed)

ORG
ECO        REVISED
ITEM                        ALTERNATE  MESSAGE
PCA ECO-001422 700-0237-0001 Implementation failed: ENG_TRANSFER_PENDING_DG

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.