Why is adop still showing phase APPLY status ACTIVE after having applied successfully a patch using "adop phase=apply hotpatch=yes"?
There were no errors in the adop patch logs. 
But adop status still shows:

Node Name    Node      Type         Phase       Status                 Started                             Finished
-----------   ----       ----------  -----        ---------------     --------------------------  -------------------
node_name                master       PREPARE    NOT APPLICABLE
                                                 APPLY        ACTIVE                19-SEP-14 09:18:18 -04:00 19-SEP-14 09:24:05      <<<< APPLY phase is still ACTIVE
                                                 FINALIZE    NOT STARTED
                                                 CUTOVER   NOT APPLICABLE
                                                 CLEANUP    NOT STARTED


One cannot run adop phase=cutover because there are no Online Patching cycle was started.
The patch was applied in hotpatch=yes mode on the RUN filesystem.
 

Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.