R12 - Edit Budget Using Web ADI (Project Budget Periodic) Displaying Content Form values In Version 12.2.3 (Doc ID 1934425.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Planning and Control - Version 12.2.3 and later
Oracle Project Resource Management - Version 12.1.3 to 12.1.3 [Release 12.1]
Information in this document applies to any platform.

Symptoms

When editing a Periodic Budget using Web ADI from a plan, on version 12.2.3, the Content page is displayed with the mapping value "Periodic Budget Content" and 3 fields that are not expected. For example, the user can see : 7012,14138,Y.

This page should not be displayed as this is a simple export.

STEPS
-----------------------
Financial > Budgets and Forecasts > Maintain Budget Versions - Actions : Edit in Excel