Publishing A Workplan Sets Chargeable Option To 'N' For Some Tasks
(Doc ID 1960630.1)
Last updated on NOVEMBER 28, 2023
Applies to:
Oracle Project Planning and Control - Version 12.1.3 and laterInformation in this document applies to any platform.
Symptoms
PRC: Process Structure Updates is changing Chargeable Flag on existing task when creating new tasks.
- happening only on Published Structures
- Initially Tasks have chargeable flag set to 'Y'.
The workplan is published after a new task is created.
Once the workplan is published, certain tasks automatically switch the chargeable option to 'N'.
- Not all tasks are changed
- Only happens when workplan is published
Cause