R12: Publishing Workplan Gives Error: You Have Charged A Supplier Invoice To This Task With A Finish Date That is After the Task Finish Date

(Doc ID 1969071.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Planning and Control - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

User is trying to extend the task finish date on the workplan.
When they go to publish the workplan they get the following error: "You have charged a supplier invoice to this task with a finish date that is after the task finish date. Please revise the task finish date so that it is the same or later than the supplier invoice finish date: 'DD-MON-YYYY'."

You have searched all the expenditure items that have been charged to the project and cannot find any problem expenditure items.

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms