Last updated on MARCH 08, 2017

Applies to:

Oracle Project Billing - Version 12.2.3 and later
Information in this document applies to any platform.
PRC: Generate Draft Revenue for a Single Project

Symptoms

On Release 12.2.x:

1. Create a Contract Project. Say Project# 1111

2. Create funding to that project through 2 different agreements:
      Agreement A1 for $30,000
    Agreement A2 for $70,000


3. Run PRC: Generate Draft Revenue for this project.
   This created 2 automatic revenue events with agreements stamped on it:
       Event E1 - $30,000 (with agreement A1 stamped)
    Event E2 - $20,000 (with agreement A2 stamped)
   
   This is fine.

The issue is that there is only 1 revenue header generated with agreement A2 stamped on it.
This revenue has 2 revenue lines, one pointing to agreement A1 and another pointing to agreement A2.
This is wrong.

The expectation would be that since there are 2 automatic events pertaining to 2 different agreements (per the fix in Bug 18828683)
revenue generation should honor the agreement information and create 2 draft revenues, one per agreement.

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Cause
Solution
References


This document is being delivered to you via Oracle Support's Rapid Visibility (RaV) process and therefore has not been subject to an independent technical review.
My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.