No Funds Available At The Project Level For Project When PO Created in Prior Year Was Canceled in Current Year (Doc ID 2044061.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Project Costing - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

On : 12.1.3 version, Funds Check

No funds available at the Project Level for Project 10350

A PO was created against this project. All the lines on the PO are dated for period of MAY-15 and the budget is in SEP-14, Two lines were passing and one line was failing the funds check.

The PO was cancelled and the a PRC Update was run for the Project. The Budget was adjusted and funds moved to Jun-15. The budget was then submitted and Baselined. (Budget Status is rejected)

A requisition was then created for the same items stated (this requisition is incomplete).

The Requisition is failing funds check at the Project Level (in the current working budget the funds are in Sep-14)

Cause

Sign In with your My Oracle Support account

Don't have a My Oracle Support account? Click to get started

My Oracle Support provides customers with access to over a
Million Knowledge Articles and hundreds of Community platforms