When an item is planned, the need_by_date column is required. However, on core requisition forms, a purchase requisition (PR) can be approved for plan item without need_by_date populated on the form.
Steps To Reproduce
1. Create an item in master organization V1 as not planned
Navigate > Items > Master Items
Tab: MPS/MRP Planning, see Planning Method = unplanned
2. Assign item to inventory organization M1. Then make item planned on M1 organization
Navigate > Items > Master Items
Tab: MPS/MRP Planning, see Planning Method= MRP/MPP Planned
3. Create a PR from requisition form, choosing the plan item first.
Navigate > Requisitions > Requisition
a. Enter line 1 information, see Need-By is not required (white background).
b. At the page bottom section of form, change the ship to org (Field 'Location') from V1 to M1.
c. At this point, the need_by_date field is a mandatory field and it should be changed to yellow (mandatory).
but the behavior at the form is the need_by_date field will not change from white (optional) to yellow (mandatory).
It is still an optional field, so user can approve the PR without populating the need_by_date.
Changes
Cause
To view full details, sign in with your My Oracle Support account. |
|
Don't have a My Oracle Support account? Click to get started! |
In this Document
Symptoms |
Changes |
Cause |
Solution |
R12.1.3 |
R12.2.4 |
References |