Why is the Cycle Count Generating Report Created on Weekends, when Calendar is only 5 days a week?

(Doc ID 2058353.1)

Last updated on SEPTEMBER 21, 2015

Applies to:

Oracle Inventory Management - Version 12.1.3 and later
Information in this document applies to any platform.

Goal

Is to run the Cycle Count only during the week, not on weekends.

Solution