In an OPM Outside Processing (OSP) Batch, Why Is Actual Process Qty Blank after Running Resource Transactions Manager (Doc ID 2065959.1)

Last updated on MARCH 08, 2017

Applies to:

Oracle Process Manufacturing Process Execution - Version 12.2.4 and later
Information in this document applies to any platform.

Goal

When using OPM OSP, after running the Resource Transactions Manager, the resource transaction is created correctly and the resource actual usage is updated correctly, but the Actual Process Qty is left blank.
 

Solution