My Oracle Support Banner

Is it Possible To Update Promise Date Automatically In PO Line As Per ASN Expected Arrival Date ? (Doc ID 2092971.1)

Last updated on FEBRUARY 18, 2021

Applies to:

Oracle Inventory Management - Version 12.2 and later
Information in this document applies to any platform.

Goal

Is there a functionality to update Promise date automatically in PO Line as per ASN expected arrival date.

For example: Supplier Promise date: 15 Dec 2015 because of some reason (shipment delayed/ supplier shipped late) shipment is delayed and expected receipt date is delayed to 18 Dec 2015, this date should be updated automatically in PO line promise date so Promise date and ASN date should be in Sync.


Solution

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Goal
Solution


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.