R12: Not Able To Baseline Draft Revenue Budget
(Doc ID 2117842.1)
Last updated on SEPTEMBER 24, 2024
Applies to:
Oracle Project Billing - Version 12.1.3 and laterInformation in this document applies to any platform.
Symptoms
When attempting to baseline a draft revenue budget, the following error occurs.
ERROR
-----------------------
Task funding is not equal to the budget total of the task. To baseline a draft budget, the budget total must be as same as funding total
Changes
Cause