R12 Cannot Remove Finish Date From Project Tasks In PAXPREPR Form (Doc ID 2132224.1)

Last updated on JUNE 26, 2017

Applies to:

Oracle Project Foundation - Version 12.1.3 and later
Information in this document applies to any platform.

Symptoms

We are unable to remove the end-dates from the Project Tasks in Projects form PAXPREPR as we receive the following error message:


When we check the task again, Task End Date is still available and not allowing us to end-date even after multiple attempts.
This occurs only when there are high number of tasks and trying to modify entire list of tasks at once.

Cause