My Oracle Support Banner

Cannot Change The Project And Task To Null And Task To Null Using The Work In Process (WIP) Mass Load (Doc ID 2165812.1)

Last updated on JULY 15, 2024

Applies to:

Oracle Work in Process - Version 12.2.3 and later
Information in this document applies to any platform.

Symptoms

When attempting to update Work Order Header Project ID and Task Id to null using the WIP Mass Load, the following error occurs.

ERROR
Error: Invalid value for Project.

  Possible Causes:

  1. No such project currently exists.
  2. Project References are not enabled in your organization.

STEPS
The issue can be reproduced at will with the following steps:
1. Update the WIP_JOB_SCHEDULE_INTERFACE table PROJECT_ID and TASK_ID columns with FND_API.G_NULL_NUM
2. Launch Mass Load for row
3. Update the WIP_JOB_SCHEDULE_INTERFACE table PROJECT_ID and TASK_ID columns with FND_API.G_NULL_CHAR
4. Launch Mass Load for row

Changes

 

Cause

To view full details, sign in with your My Oracle Support account.

Don't have a My Oracle Support account? Click to get started!


In this Document
Symptoms
Changes
Cause
Solution
References


My Oracle Support provides customers with access to over a million knowledge articles and a vibrant support community of peers and Oracle experts.